Holland Point: Revetments



Project Manager: Walter O’Connor III
Client: Holland Point Citizens Association, Inc
Completion Date: September 12, 2009
Contract Amount: $530,715.19
Project Duration: March 16, 2009 to September 12, 2009

The Holland Point Citizens Association, Inc contracted Environmental Quality Resources, LLC to construct approximately 2,665 linear feet of stone reinforcement repair between Maple Ave and Hemlock Ave in Anne Arundel County, MD.

The reinforcements are to be constructed in a way that they do not damage present pier and bulkhead piles. In addition, existing surface and subsurface drainage pipes are to be incorporated into the final structure. Utilizing six to eighteen-hundred pound armor stones, EQR is involved in the installation a continuous revetment along the site, following the removal of the existing bulkhead. Following construction, all disturbed ground is to be stabilized and restored.